| GPU die power reduction | Up to 21% | measured | NVIDIA H100 NVL, 48 hours, managed and baseline arms under an equal cap, NVML die power. A lower bound on wall power. |
|---|
| Tokens per watt | Up to +22% | derived | Balanced mode, from NVML die power and vLLM serving throughput on the same 48-hour run. |
|---|
| Throughput change in the run | 0% | derived | Same 48-hour run. |
|---|
| Reduction at the metered plane | About 15% to 21% | modelled | 21% times the 72% accelerator share, conservative; 21% as a floor on wall watts, stated basis. |
|---|
| Reduction the requirement needs | About 11% | modelled | One minus 4,000 over 4,480. |
|---|
| Racks inside 4 MW without the runtime | 28 racks, 2,016 accelerators | modelled | 4,000 over 140, rounded down, times 72. |
|---|
| Shortfall without the runtime | 4 racks, 288 accelerators | modelled | 2,304 less 2,016. |
|---|
| Managed rack draw | About 119 kW to about 111 kW | modelled | 140 kW less the metered-plane reduction, conservative to stated. |
|---|
| Racks inside 4 MW with the runtime | 33 to 36 racks, 2,376 to 2,592 accelerators | modelled | 4,000 over the managed rack draw, rounded down, conservative to stated. |
|---|
| Beyond the requirement | 1 to 4 racks, 72 to 288 accelerators | modelled | Racks that fit less the 32 required. |
|---|
| Headroom inside the contract | 197 to 461 kW | modelled | 4,000 kW less the requirement's managed draw of about 3,803 kW or about 3,539 kW. |
|---|
| Fit floor on accelerator share | 51% | modelled | The about 11% needed, over 21%. The fit holds at any share at or above it. |
|---|
| Fleet mean draw | 3,040 kW | modelled | 32 racks at 95 kW. |
|---|
| Continuous demand avoided | About 253 to 351 kW | modelled | 3,040 kW times the metered-plane reduction times the 55% busy share. Idle and pinned hours get nothing. |
|---|
| Energy a year | About 2,200 to 3,100 MWh | modelled | Demand avoided over 8,760 hours. |
|---|
| Money a year | About GBP 440,000 to GBP 620,000 | modelled | At the illustrative 20 pence. The tenant's under a wholesale lease at cost; the landlord's under a bundled licence. |
|---|
| Share of the tenant's colocation bill | About 4% to 5% | modelled | The metered-plane reduction times a power share of about a quarter, taken from one operator's disclosed segment. |
|---|
| More accelerators inside the same 4 MW | About 18% to 29% | modelled | 33 or 36 racks against 28. Rack-count arithmetic, never added to the bill percentage. |
|---|
| Draw to cover on a total runtime failure | 480 kW at the 32-rack requirement; 620 to 1,040 kW at 33 to 36 racks | modelled | Unmanaged racks at 140 kW against a 4,000 kW contract: 4,480 kW at 32 racks, 4,620 or 5,040 kW at 33 or 36. Covered by an agreed curtailment right, reserved headroom, or a commitment set below the modelled figure. |
|---|
| Accelerator-share sweep | 100%: 36 racks. 85%: 34 racks. 72%: 33 racks. 51%: requirement met. 45%: one rack short | modelled | One input swept, everything else held. The 100% row is the stated basis. |
|---|
| At ten times the scale | 40 MW, 320 racks: 285 racks unmanaged, 336 to 361 with the runtime, about 22,000 MWh a year | modelled | Same arithmetic; 16 racks and 1,152 accelerators beyond the requirement on the conservative reading. |
|---|